Middlesex Turnpike Roadway Reconstruction Project in Bedford & Billerica 

Similar work will take place in the project from April 16 to 27 – Image (c) JMcCT, 2018 all rights reserved – Click to view larger image

Submitted by the Bedford Department of Public Works

Traffic Notice  – April 16 thru April 27

On-road work is scheduled for Manning Road and Lexington Road (extension of Old Billerica Road in Bedford) and along Middlesex Turnpike between Manning Road & Lexington Road, weather dependent.

Reclamation Work on Lexington Road and Manning Road:

  • Tuesday, 4/16, 7am – 3pm (work will require alternating traffic patterns)
  • Wednesday, 4/17, 7am – 3pm (work will require alternating traffic patterns)

Paving Work on Middlesex Turnpike, Manning Road and Lexington Road

Get The Bedford Citizen in your inbox!



  • Monday night, 4/22, 7pm – 6am  (work will require that Lexington Road be closed off and traffic detoured to Manning Road)
  • Tuesday night, 4/23, 7pm – 6am (work will require alternating traffic patterns)
  • Wednesday night, 4/24, 7pm – 6am (work will require that Lexington Road be closed off and traffic detoured to Manning Road)
  • Thursday night, 4/25, 7pm – 6am (work will require alternating traffic patterns)
  • Friday night, 4/26, 7pm – 6am (will require alternating traffic patterns)
  • Possibly Saturday, 4/27, 7am3pm, if additional time to complete the planned paving work is required.

 

 

 

Print Friendly, PDF & Email
Subscribe
Notify of

0 Comments
Inline Feedbacks
View all comments

All Stories

What’s Bedford Thinking? Are you going to watch the movie "Challengers?" If so, how?   

View Results

Loading ... Loading ...
  • Junior Landscaping
Go toTop